Timeline

October 2014

  • CLC concept designs submitted by potential architects

November 2014

  • Jury review of semi-finalists
  • Finalists announced

January/February 2015

  • Dialogue sessions with finalists

March 2015

April 2015

October 2015

  • Complete programming phase

February 2016

  • Complete schematic design

September 2016

  • Complete design development

October 2016

April 2017

  • Complete construction documents
  • Finish construction of DUC-ling dining center

May 2017

  • Move-out of DUC west wing
  • Dining moves into DUC-ling
  • Demolition of DUC west wing begins

May 2019

  • Opening of new Campus Life Center